Magnetic Resonance

Anna-Laberge Hospital

The Anna-Laberge hospital proceeded with the replacement of its magnetic resonance imaging scanner (MRI) in the summer of 2015. The project included the dismantling, construction and start-up of the new MRI scanner by Siemens. The  total project construction cost including the biomdelical equipment was $1,5M in  and it had to accomplished in less than 10-weeks to minimize the loss of service for the patients of the hospital.

For this project, Enertech acted as the project manager and fulfilled the mandate of managing the budget, schedule and the scope of work. Completed on time and without cost overruns, the project was marked by a major challenge: commissioning the MRI’s cooling equipment to ensure stable operating conditions, as provided by both Enertech and the project’s engineering consultants. A great success for Enertech and the Anna-Laberge Hospital, both on the technical and budgetary fronts!

Budget: 1.5M$
Timeline:
May 2015 - July 2015 (3 months)